Notice to Residents on W 3rd Street and Surrounding Areas
BOROUGH OF PALMYRA CONTRACTOR: COASTLINE EXCAVATING LLC
BOROUGH OF PALMYRA ENGINEER: ENVIRONMENTAL RESOLUTIONS, INC.
THIS NOTICE IS TO INFORM YOU THAT STARTING MONDAY, OCTOBER 14, 2024 WEATHER PERMITIING, ROAD CONSTRUCTION WILL TAKE PLACE ON YOUR STREET. WE WILL INTIALLY START WITH SAWCUTTING THE ROADWAY & MOBILIZING INTO PROJECT. HOWEVER, EXCAVATION WILL NOT START UNTIL WEDNESDAY, OCTOBER 16, 2024.
THE 1ST PHASE OF CONSTRUCTION WILL INCLUDE THE INSTALLATION OF 12″ SEWER MAIN & SEWER LATERALS.
PLEASE NOTE THAT PRIOR TO CONSTRUCTION WE ARE REQUIRED TO CALL IN UTILTIY MARKOUTS. IT IS IMPERATIVE THAT THE MARKO UT FLAGS LEFT BY THE UTILITY COMPANIES REMAIN IN PLACE AND SHOULD NOT BE REMOVED BY HOMEOWNERS AND/OR LANDSCAPING CONTRACTORS. THIS WORK SHOULD BE COMPLETED WITHIN 3 WEEKS.
THE HOURS OF OPERATION FOR THIS WORK WILL BE 7:00 AM TO 5:00 PM WE ASK FOR THE ROADWAY TO BE CLEAR OF ANY PARKED CARS DURING THE MENTIONED WORK HOURS.
WE APOLOGIZE FOR THE INCONVENIENCE THAT THESE OPERATIONS MAY PRESENT AND THANK YOU IN ADVANCE FOR YOUR COOPERATION AND PATIENCE. IF YOU HAVE ANY QUESTIONS OR CONCERNS, PLEASE DO NOT HESITATE TO CONTACT THE FOLLOWING.
COASTLINE EXCAVATING LLC: KEVIN SCHOEBER 856-986-8363